Planning & Development
Building Inspections
The District of Logan Lake Building Inspection Services are facilitated by staff from the Thompson-Nicola Regional District. For further information please click here. To view District of Logan Lake Building Regulations Bylaw 602, please click here.
A Building Inspector is in the District Office on Thursdays from 9:30am-11:00am. To book an inspection please visit the TNRD Site at www.tnrd.ca.
Development Guide
Please see the following documents at the bottom of the page:
- Land Development Guide
- Development Approval Procedures Bylaw
- Chartrand Commercial Opportunity
- Ironstone Ridge
Engineering Services
The District of Logan Lake Engineering Services are facilitated by True Consulting Group. Please direct inquiries to the Chief Administrative Officer at 250-523-6225 (229).
Land Development
Welcome to Land Development Procedures in Logan Lake.
The Local Government Act and Community Charter govern how municipal governments can manage land development by using the following tools and procedures:
Council Approval
- Official Community Plan Bylaws
- Zoning Bylaws
- Development Permits
- Development Variance Permits
- Temporary Commercial and/or Industrial Use Permits
Independent Board Approval
- Board of Variance
Approving Officer Approval
- Subdivisions
The following briefly describes the above bylaws, permits and approval procedures, that staff will assist you with.
Official Community Plan Bylaw:
The Official Community Plan Bylaw (OCP), is a general statement of the District's broad objectives and policies with respect to the form and character of existing and proposed land use. The OCP includes policies regarding economic, social and environmental objectives and contains land use designations.
An OCP bylaw and/or amendment requires a Public Hearing and is approved by Council.
Zoning Bylaw:
The Zoning Bylaw governs the use and density of land, buildings and structures; the area, shape and dimensions of parcels of land; floodplains and parking and loading provisions, in order to guide development of land in an efficient, systematic and orderly way for the benefit of the community.
A Zoning bylaw and/or amendment requires Public Hearing and is approved by Council.
Development Permits:
An Official Community Plan Bylaw may designate Development Permit Areas within a municipality; and a Development Permit Area may establish guidelines for the form and character of a development.
Development Permits are: required before land is subdivided or construction of an addition to, or alteration of, a building or structure is commenced; are granted by Council; noted on title of the said property; and, are binding on all persons who acquire an interest in the property.
Development Variance Permits:
Development Variance Permits may be used to vary the provisions of various bylaws (i.e. Zoning, Subdivision, Land Use) with respect to siting, design, servicing or environmental features, but cannot vary the use or density of land or floodplain specifications.
Development Variance Permits require a public process; are granted by Council; are noted on title of the said property; and are binding on all persons who acquire an interest in the property.
Temporary Commercial and/or Industrial Use Permits:
Temporary Commercial and/or Industrial Use Permits may be issued in relation to land designated in an Official Community Plan, to allow a use not permitted by a Zoning Bylaw. They specify conditions under which the temporary use may be carried out and/or allow and regulate the construction of buildings or structures in respect of the use for which the permit is issued.
Temporary Commercial and/or Industrial Use Permits require a public process; are granted by Council; are noted on title of the said property; and are binding on all persons who acquire an interest in the property.
Board of Variance:
The Board of Variance is a mandatory, independent, and impartial body whose purpose is to consider minor variances of Zoning Bylaw regulations that would cause an undue hardship to the applicant. The Board of Variance cannot vary permitted uses or densities under a Zoning Bylaw, nor can it deal with major variations that should be the subject of a Development Variance Permit.
A Board of Variance requires a public process and the decisions are final -- Council cannot be consulted on Board of Variance issues.
Subdivisions:
A subdivision means the adjustment of parcel lines on a specific parcel of land. There are two types of subdivisions - minor and major. A minor subdivision consists only of a lot line adjustment, lot consolidation or highway widening. A major subdivision is defined as all other subdivisions and always requires a subdivision plan. Typically, a major subdivision includes the creation of two or more parcels of property where only one existed previously.
Subdivisions are processed by the Approving Officer as per Subdivision, Zoning and applicable bylaws - Council cannot participate in subdivisions. For a copy of our Subdivision Bylaw 643 please, click here
Land Development Applications and Fees
For a copy of our Development Approval Procedures Bylaw 714 please, click here
Land Development Bylaws
For a copy of our Land Development Bylaws please click on your selection below:
• Official Community Plan Bylaw 670
Time Table for Land Development Applications
The following table provides a guide only to the estimated time periods and required steps in processing various land development applications, within the District:
P Required v May be required
Procedure(s) |
Amend OCP Bylaw |
Amend Zoning Bylaw |
Board of Variance |
DP |
DVP |
TCIU Permit |
Minor Sub- division |
Major Sub- division |
Estimated time frame (in weeks) |
4 to 12 |
4 to 12 |
4 |
4 to 12 |
4 to 12 |
4 to 12 |
|
|
Payment of Fees required |
$350 |
$350 |
$150 |
$100 |
$150 |
$450 |
P |
P |
Preliminary discussion with Approving Officer |
P |
P |
P |
P |
P |
P |
P |
P |
Application and submission of documents |
P |
P |
P |
P |
P |
P |
P |
P |
Initial consideration by Council |
P |
P |
|
P |
P |
P |
|
|
In-house technical review |
P |
P |
|
P |
P |
P |
P |
P |
Referral to outside agencies |
P |
v |
|
v |
v |
v |
v |
v |
Staff report to Council (draft permit, etc.) |
P |
P |
|
P |
P |
P |
P |
P |
Consideration by Council to proceed |
P |
P |
|
P |
P |
P |
P |
P |
Public notification process |
P |
P |
P |
|
P |
P |
|
|
Public or statutory hearing |
P |
P |
P |
|
P |
P |
P |
P |
Third reading and adoption of bylaw(s) |
P |
P |
|
P |
P |
P |
P |
P |
Notice to applicant of Council decision |
P |
P |
|
P |
P |
P |
P |
P |
Permit to Land Titles for registration |
|
|
|
P |
P |
P |
|
|
Survey of submission |
|
|
|
|
|
|
P |
|
Final approval of plans |
|
|
|
|
|
|
P |
|
Registration of subdivision |
|
|
|
|
|
|
P |
|
Submission of registered plans |
|
|
|
|
|
|
P |
|
Design review |
|
|
|
|
|
|
|
v |
Evidence of liability insurance |
|
|
|
|
|
|
|
P |
Issuance of construction permit |
|
|
|
|
|
|
|
P |
Construction of works |
|
|
|
|
|
|
|
P |
Inspection and submissions of required info |
|
|
|
|
|
|
|
P |
Final review/provisional acceptance of work |
|
|
|
|
|
|
|
P |
Maintenance Bond |
|
|
|
|
|
|
|
v |
Final approval |
|
|
|
|
|
|
|
P |
Registration of subdivision |
|
|
|
|
|
|
|
P |
Agreement to construct by specified date |
|
|
|
|
|
|
|
v |
Contact Information:
For further information and/or assistance with land development please contact the Chief Administrative Officer at the contacts below or by stopping in at our office Monday to Friday, excluding statutory holidays, during regular business hours, at #1 Opal Drive, Logan Lake, BC. Closed for lunch from 12:30 to 1:00 p.m.
PO Box 190
#1 Opal Drive
Logan Lake, BC V0K 1W0
P: 250-523-6225 ext. 229
Send Email
Download Documents
- Development Approvals PackageUploaded: May 12, 2016
- Land Development GuideUploaded: May 12, 2016
- Chartrand Commercial OpportunityUploaded: May 12, 2016
- Ironstone RidgeUploaded: May 12, 2016
- Development Approval ApplicationUploaded: October 30, 2020